Union Station
Location:
Union Station, 55 Front Street, Toronto, Ontario
Duration:
2011 to 2015
Shoring Contractor:
Belor Construction – Earthline Foundations
Services Provided
Over a five-year period, InGeo Design played a critical role in supporting major underground excavation and tunnel rehabilitation work along Front Street in downtown Toronto, between Bay and York Streets. As a design subconsultant, we delivered quick-turnaround, implementation focused solutions in one of the city’s busiest infrastructure corridors offering direct access to key personnel to support EllisDon and structural engineers.
This urban project required excavation around and over the active TTC tunnel, in close proximity to aging buildings and complex utility networks. Designs had to be produced quickly, adapted frequently, and coordinated with multiple teams, all while maintaining structural safety and minimizing disruption to downtown operations.
Key Challenges
- Maintaining tunnel integrity across multiple excavation stages
- Accommodating heavy construction and crane loads above existing structures
- Avoiding conflicts with dense and unpredictable utility layouts
- Providing clear connection details to existing buildings
- Ensuring close communication between field and design teams
InGeo’s Role & Scope
- Direct access to key InGeo engineers, enabling real-time decision-making and responsive collaboration
- Detailed structural connection design between shoring systems and adjacent buildings
- Utility coordination, proactively addressing conflicts with water mains, sewers, telecom lines, hydro duct banks, and gas
- Finite element analysis (FEA) of TTC tunnels during staged excavation
- Lateral bracing design and modeling using SAP2000
- Shoring system design: soldier piles & lagging, caisson walls, shotcrete, tiebacks, struts, rakers, and corner braces
- Temporary support systems for tunnel rehabilitation and utility protection
- Traffic decking design at Bay & Front intersection to maintain safe vehicle/pedestrian flow
- Design of a platform for a mobile crane, considering load transfer to underlying structures and utilities
- Design of micropiles to support vertical loading from rakers in constrained spaces
- Load analysis for tunnel structure under mobile cranes and heavy construction equipment
- Field engineering presence for tieback stressing, raker and strut preloading, flat jack testing, column loading, and rapid issue resolution
More Projects

Union Station
Complex Excavation Support & Tunnel Rehabilitation:
Front Street Corridor – Toronto, ON... Read More

Royal Canadian Yacht Club Seawall
Seawall and Boat Lift Replacement for Expanded Marine Access
Royal Canadian Yacht Club – Toronto Islands, Toronto, ON... Read More

Essa Road Expansion
Excavation Shoring for Interchange Reconstruction and Bridge Replacement
Highway 400 & Essa Road – Barrie, ON... Read More

Highway 407 Expansion Over Wilcot Creek
Excavation Shoring for Bridge Construction on Major Highway Expansion
Highway 407 at Wilcot Creek – Clarington, ON... Read More

West Portal - Eglinton Crosstown LRT
Excavation Shoring & Monitoring for Major Transit Infrastructure
Eglinton Avenue West – West of Black Creek Drive, Toronto, ON... Read More

Dundas And Aukland Condominium
Urban Excavation Shoring & Monitoring for High-Rise Mixed-Use Tower
5249 Dundas Street West – Etobicoke, ON... Read More

2175 Keele Street Phase II
Excavation Shoring & Monitoring for Large-Scale Mid-Rise Residential Development
2175 Keele Street – Toronto, ON...Read More

Queen & Ontario Condominium
261–285 Queen St. E., 90 Ontario St. & 384–410 Richmond St. E. – Toronto, ON... Read More

Toronto Western Hospital
Excavation & Monitoring Support Design for Hospital Expansion: Bathurst Street & Nassau Street – Toronto, ON... Read More

Catharine Street Pedestrian Bridge
Specialized Foundation Design & Load Testing for Municipal Bridge Replacement
1 Catharine Street, Belleville, ON... Read More

Dofasco Steel Plant Micropiles
Micropile Design & Testing for Major Industrial Expansion
1330 Burlington Street East – Hamilton, ON... Read More

900 St. Clair Avenue West
Urban Excavation Shoring & Monitoring for Mixed-Use Development
898–900 St. Clair Avenue West, Toronto, ON... Read More

Beckett Sproule Pumping Station
Shoring Design and Monitoring for Critical Water Infrastructure Upgrade - 321 Heart Lake Road South – Brampton, ON... Read More

Adelaide St. N. Underpass
Caisson and Soldier Pile Excavation Support Design for Rail Underpass Construction: Central Avenue & Adelaide St. North – London, ON...Read More

TTC Donlands Subway Station
Donlands TTC Station – Toronto, ON... Read More

5250 Yonge Street
Excavation Shoring and Monitoring Adjacent to TTC Subway Infrastructure
5250 Yonge Street – Toronto, ON... Read More

939 Eglinton Ave East - Upper East Village Condos
Urban Excavation Shoring & Monitoring Adjacent to Critical Transit Infrastructure
939 Eglinton Avenue East – Toronto, ON... Read More

Regent Park Block 17S
Urban Excavation Shoring & Monitoring for High-Rise Residential Tower
Northwest Corner of Dundas Street East & River Street – Toronto, ON... Read More

HIGHWAY 401 and raisin river
Cofferdam Shoring for Bridge Replacement Over Active Watercourse
Intersection of Highway 401 & Raisin River – South Glengarry, ON... Read More